Google stopped building a data center in Belgium after authorities refused to allow it.
Google announced the suspension of construction work on a data center in southern Belgium after authorities ordered it to stop because the project did not receive necessary permits and required modifications.

Google announced on Saturday the suspension of construction for a new data center in southern Belgium. This announcement came in response to the regional authorities ordering an immediate halt to work due to incomplete permitting procedures for the project. The company’s official spokesman denied any shortcomings, stressing that the shutdown is in full compliance with the guidelines of local authorities where it has been operating for more than 15 years with constant care to comply with applicable laws.
The reason for the shutdown and the building permit dispute.
A spokesperson for Google points out that the dispute erupted this year when the company requested to modify the terms of a building permit it officially received from authorities in 2024. This request included expanding the centre’s area and allowing water from the Sambre River to be used to cool equipment instead of relying on an air system as was planned in the original plan. The regional authorities of Wallonia rejected the request for amendment following strong local opposition to the proposal, which led Google to appeal the decision in court.
Legal details and court timetables
Nikola Jerno, spokesman for the regional authorities of Wallonia, explained that the dispute is about the legality of the required amendments which have not been approved by the local government. Google is currently facing any new instructions from the authorities before resuming any activity on the site. A court hearing is scheduled for January to consider the company’s appeal against the closure decision. The results of this session will determine the next step for the project in Belgium.
- Google has stopped construction of the center.
- Belgian authorities have ordered a halt because there are not enough permits .
- A court hearing is scheduled for January.